1. A and B complete a work in 6 days. A alone can do it in 10 days. If both together can do the work in how many days?

a) 2.75 days
b) 3.75 days
c) 4.75 days
d) 5.75 days

Explanation:

1/6 + 1/10 = 8/30 = 4/15

15/4 = 3.75 days

2. A and B together can do a piece of work in 8 days. If A alone can do the same work in 12 days, then B alone can do the same work in?

a) 24 days
b) 14 days
c) 36 days
d) 30 days
 

Explanation:

B = 1/8 – 1/2 = 1/24 => 24 days

3. A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it?

Source: safalta.com



a) 15 days
b) 25 days
c) 10 days
d) 20 days

Explanation:

C = 1/2 - 1/4 - 1/5 = 1/20 => 20 days


4. A and B can do a piece of work in 6 2/3 days and 5 days respectively. They work together for 2 days and then A leaves. In how many days after that B will complete the work alone.

Free Demo Classes

Register here for Free Demo Classes



a) 4 ½ days
b) 3 ½ days
c) 1 ½ days
d) 2 ½ days

Explanation:

3/20 * 2 + (2 + x)/5 = 1
x = 1 ½ days

5. A can do a piece of work in 30 days. He works at it for 5 days and then B finishes it in 20 days. In what time can A and B together it?

a) 11 (1/3) days
b) 12 (1/3) days
c) 13 (1/3) days
d) 14 (1/3) days
Explanation:

5/30 + 20/x = 1
x = 24
1/30 + 1/24 = 3/40

40/3 = 13 (1/3) days

6. A and B can do a piece of work in 12 days and 16 days respectively. Both work for 3 days and then A goes away. Find how long will B take to complete the remaining work?

a) 6 days
b) 12 days
c) 9 days
d) 8 days
Explanation:

3/12 + (3 + x)/16 = 1

x = 9 days

7. A and B can do a piece of work in 3 days, B and C in 4 days, C and A in 6 days. How long will C take to do it?

a) 24 days
b) 12 days
c) 18 days
d) 30 days

Explanation:

2c = ¼ + 1/6 – 1/3 = 1/12

c = 1/24 => 24 days

8. A can do a piece of work in 10 days. He works at it for 4 days and then B finishes it in 9 days. In how many days can A and B together finish the work?

a) 10 days
b) 18 days
c) 6 days
c) 12 days
Explanation:

4/10 + 9/x = 1 => x = 15

1/10 + 1/15 = 1/6 => 6 days

9. A can do a piece of work in 40 days; B can do the same in 30 days. A started alone but left the work after 10 days, then B worked at it for 10 days. C finished the remaining work in 10 days. C alone can do the whole work in?

a) 36 days
b) 12 days
c) 18 days
d) 24 days

Explanation:

10/40 + 10/30 + 10/x = 1

x = 24 days

10. A work which could be finished in 9 days was finished 3 days earlier after 10 more men joined. The number of men employed was?

a) 20
b) 30
c) 10
d) 40

Explanation:

x ------- 9
(x + 10) ---- 6
x * 9 = (x + 10)6

x = 20

 

Related Article

IBPS Calendar 2025: आरआरबी क्लर्क, पीओ सहित विभिन्न परीक्षा के लिए तिथियां घोषित, यहां देखें पूरा शेड्यूल

Read More

CFA Level 1 Results 2024: आ गया नवंबर सत्र के लिए सीएफए लेवल-1 परीक्षा का रिजल्ट; पास प्रतिशत 43 फीसदी रहा

Read More

DHSE Kerala Plus Two, Class 11 Model Exam Time Table 2025 released, Check the exam schedule here

Read More

Maharashtra RTE Admission: 25% आरक्षित सीटों पर महाराष्ट्र आरटीई के लिए आवेदन शुरू, जानें पात्रता मानदंड

Read More

SBI PO Job 2024: एसबीआई में पीओ के 600 पदों पर आवेदन की अंतिम तिथि बेहद नजदीक, जल्द करें इस लिंक से पंजीकरण

Read More

UKPSC RO, ARO Prelims Exam: यूकेपीएससी आरओ, एआरओ प्रारंभिक परीक्षा हुई रद्द, अब इस डेट में होगा एग्जाम

Read More

RRB NTPC Exam 2024: कब जारी होगी आरआरबी एनटीपीसी परीक्षा की तारीख? जानें परीक्षा से जुड़े नए अपडेट्स

Read More

GATE 2025 Admit Card: गेट परीक्षा के लिए प्रवेश पत्र हुए जारी, यहां से करें डाउनलोड; फरवरी में होंगे एग्जाम्स

Read More

JAC Jharkhand board 10th-12th model papers 2025 out; Read the steps to download pdf here

Read More